South Carolina’s Court of Appeals has made it crystal clear that our mechanics’ lien statutes must be strictly construed. In a case* refiled December 2, the Court affirmed the Circuit Court’s award of summary judgment because the lien was filed 91 days after the last work was performed, not 90 days, as the statute requires.
The case involved a kitchen remodel job in Columbia. The contractor was a kitchen designer who was paid not by the hour, but by the difference in the wholesale and retail cost of the products she purchased and installed. In this case, she was hired because she was the only dealer for Crystal Cabinets in the Columbia area.
The homeowner’s quote was slightly less than $50,000 plus about $3,000 for cabinet installation, payable in three installments. The homeowners paid two-thirds of the contract price but refused to pay the final installment because they were dissatisfied with the cabinets. The parties and the manufacturer were unable to come to terms. The contractor’s last work, according to its own pleadings, was performed on August 18, 2015, and the mechanic’s lien was served on November 17, 2015, a difference of 91 days. The Circuit Court granted the homeowner’s motion for summary judgment and awarded attorney’s fees, based on the one-day discrepancy.
On appeal, the contractor argued that the work actually extended beyond August 18, but the Court of Appeals held the contractor was bound by the pleadings. The contractor then argued that an amendment to the pleadings could easily cure the “slight discrepancy” between the date alleged in the lien and the actual date of the last work, but the Court held that this issue could not properly be raised on appeal. The contractor should have requested leave of the lower court to amend its pleadings.
The bottom line is that counting correctly is crucial in mechanics’ lien litigation! Be careful out there, lawyers!
* The Kitchen Planners, LLC v. Friedman, South Carolina Court of Appeals Opinion 5738, Refiled December 2, 2020.